Upon completion of the construction of conveyance systems, treatment facilities, flow control facilities and structural source control BMPs (excluding the construction of on-site stormwater management BMPs) and prior to final inspection approval, the applicant shall submit record drawings of the full stormwater site plan prepared by a civil engineer or registered surveyor. The engineering drawings shall accurately represent the project as constructed. They shall depict the actual vertical and horizontal locations of roads and drainage facilities constructed on and off the site. Record drawings shall be stamped, signed and dated by a civil engineer licensed in Washington State and shall meet the standards contained in the EDDS. (Added by Amended Ord. 10-026, June 9, 2010, Eff date Sept. 30, 2010).