(1) Type A, Type C and Type D7 permits may not be renewed. All other Types of right-of-way permits may be renewed as allowed by this title.

(2) Where renewal of a permit is permitted, the renewal shall be:

(a) Limited to one renewal;

(b) Applied for within 30 days of the expiration of the original permit on an application form provided by the department;

(c) For a time period no longer than the duration of the original permit; and

(d) The duration of the renewal shall be calculated from the expiration date of the original permit.

(3) Fees for permit renewals shall be 50 percent of the total fees as provided in chapter 13.110 SCC; except that the fees for renewal of Type B1, B2, B3 and B4 permits shall be determined at the engineer’s discretion but in an amount not to exceed the total fees for the original permit.

(4) Any application to renew a permit shall be reviewed by the engineer, who may approve, deny, or approve with conditions, regardless of whether or not such conditions were contained in the prior permit.

(5) In addition to any other conditions imposed by the engineer, an application for a renewal must satisfy the following:

(a) Continued use of the right-of-way is essential to complete the work or activity previously authorized;

(b) The permit holder has complied with the conditions of the prior permit and all other applicable requirements;

(c) All required fees, charges and performance deposits have been paid by the permittee;

(d) All required insurance certificates and performance security have been filed with the county and will continue to be in effect through the requested renewal period, and, where required, beyond said period; and

(e) Continuation of the private use of the public right-of-way shall not adversely affect the public health, safety or welfare.

(6) Renewal of a Type D permit whose expiration is tied to related title 30 SCC land disturbing activity or construction permit(s), shall be renewed at the same time, and may have the same expiration date, as the associated title 30 SCC land disturbing activity permit(s). (Added by Ord. 85-051 § 3, July 3, 1985; Amended by Ord. 96-028 § 23, June 12, 1996, Eff date June 29, 1996; Amended by Ord. 10-014, Apr. 7, 2010, Eff date Apr. 29, 2010; Amended by Ord. 10-014, Apr. 7, 2010, Eff date Apr. 29, 2011; Amended by Amended Ord. 12-001, Feb. 15, 2012, Eff date Feb. 26, 2012).