Construction of frontage improvements, offsite road improvements, and access and transportation circulation improvements is required prior to approval for occupancy or final inspection, except that construction may be delayed, if allowed, with a performance security in accordance with SCC 13.10.124 or 30.84.105. When no building permit will be associated with a conditional or administrative conditional use permit, construction of improvements is required as a precondition to approval, unless some later time of construction is recommended by the county engineer and imposed by the approving authority as a condition of approval. (Added by Amended Ord. 02-064, Dec. 9, 2002, Eff date Feb. 1, 2003; Amended by Amended Ord. 10-086, Oct. 20, 2010, Eff date Nov. 4, 2010; Amended by Ord. 18-018, Mar. 28, 2018, Eff date Apr. 9, 2018).