(1) When engineered construction and land disturbing activity site plans are required pursuant to SCC 30.63B.190 and 30.63B.200, or professional inspection is required pursuant to SCC 30.63B.340 for land disturbing activity, the following final reports, plans, drawings and supplements are required at completion of all land disturbing activity and construction:

(a) A record drawing of land disturbing activity site plan prepared by the civil engineer or surveyor showing original ground surface elevations, finished grade ground surface elevations, lot drainage patterns, and the locations and elevations of stormwater drainage facilities and outlets of subsurface drains. Details of subsurface drains shall be shown on the record drawing as reported by the soils or civil engineer or land surveyor. Upon completion of all land disturbing activity and construction, the civil engineer shall sign a statement on the plan stating that to the best of their knowledge, the land disturbing activities were completed in accordance with the approved land disturbing activity site plan and permit;

(b) A report prepared by the soils engineer, retained pursuant to SCC 30.63B.340(2), which shall include locations of field density tests, summaries of field and laboratory tests, other substantiating data, and a description of any changes to the approved land disturbing activity site plan made during the land disturbing activity and their effect on the recommendations made in the approved soils engineering investigation report. The report shall include a signed statement by the soils engineer that, to the best of their knowledge, the land disturbing activity work within their area of responsibility was completed in accordance with the approved soils engineering report and applicable provisions of this chapter; and

(c) A report prepared by the engineering geologist retained pursuant to SCC 30.63B.340(2) that shall include a final description of the geology of the site, any new information disclosed during the land disturbing activity, and the effect of that information on recommendations incorporated in the approved land disturbing activity site plan. The final geology report shall include a signed statement by the engineering geologist that, to the best of their knowledge, the work within their area of responsibility was completed in accordance with the approved engineering geology report and applicable provisions of this chapter.

(2) The applicant or owner shall notify the county when the disturbed land is ready for final inspection. Final approval shall not be given by the county until all land disturbing activity and construction, including installation of all drainage facilities and their protective devices and all erosion-control measures, have been completed in accordance with the final approved land disturbing activity and stormwater site plans, and the required reports have been submitted and approved. (Added by Amended Ord. 10-023, June 9, 2010, Eff date Sept. 30, 2010).