A construction permit is required for the installation of the portion of the underground water supply piping, public or private, supplying a water-based fire protection system. The permit shall apply to all underground piping and appurtenances downstream of the first control valve on the lateral piping or service line from the distribution main to one foot above finished floor of the facility with the fire protection system. Maintenance performed in accordance with this code is not considered to be a modification and does not require a permit.

Permit Exceptions.

(1) When the underground piping is installed by the aboveground piping contractor.

(2) Underground piping serves a fire protection system installed in accordance with NFPA 13D. (Added by Amended Ord. 17-058, Oct. 18, 2017, Eff date Nov. 9, 2017; Amended by Amended Ord. 21-031, July 14, 2021, Eff date July 25, 2021. Formerly SCC 30.53A.357).