Skip to main content
Loading…
This section is included in your selections.

When, in the opinion of the engineer, an existing or proposed road is considered a public necessity, the road is practicable, the interests of the county would best be served by establishing such road as part of the county transportation system, and the engineer determines that establishment shall be by the procedures in this chapter, the engineer shall prepare an ordinance for consideration by the council to establish such road. The ordinance shall be accompanied by supporting exhibits consisting of:

(1) Where applicable, a freeholders’ petition as specified in Section 13.90.030 SCC;

(2) The engineer’s report with contents as specified in Section 13.90.040 SCC;

(3) A notice of public hearing as specified in Section 13.90.050 SCC;

(4) An itemized list of costs and expenses incurred in the examination, report, appraisal and deed preparation pertaining to the proposed establishment;

(5) A properly executed Statutory Warranty Deed conveying to Snohomish County the necessary right-of-way to support the establishment of the road;

(6) A properly filed record of survey depicting the correct right-of-way limits and road alignment. Such record must show the tracts of land over which the road passes, with the names, if known, of the several owners thereof. The record of survey shall include supporting field notes and profiles;

(7) Road construction plans in conformance with the Engineering Design and Development Standards depicting all required improvements to occur within the right-of-way. Such construction plans shall be approved by the engineer. The engineer may waive the requirement for construction plans where the establishment is of right-of-way only and the road is to be constructed at some later time and/or under a separate permit;

(8) A properly executed project improvement guarantee bond to assure proper performance of road improvements constructed in conjunction with the establishment process. The engineer may waive the requirement for a project improvement guarantee bond where the establishment is of right-of-way only and the road is to be constructed at some later time and/or under a separate permit;

(9) Any exhibits and other documentation deemed necessary by the engineer to adequately explain the proposed establishment of the road. (Added by Ord. 96-028 § 65, June 12, 1996, Eff date June 29, 1996).