Skip to main content
Loading…
APPENDIX C Supportive City Street Improvements
This appendix is included in your selections.

Various cities are proposing to enhance capacity and traffic flow on city streets by significantly widening lanes, adding through and/or turn lanes, adding walkways, improving positive guidance and implementing traffic control revisions. The primary intent of these improvements is to enhance existing street capacity in order to safely and efficiently handle existing and future traffic on city streets. A secondary benefit to Snohomish County is that many of these city street improvements will help handle traffic generated by the county’s planned land use and the associated growth.

Appendix C presents various improvements to city streets to serve the city’s planned land use and that are supportive of the county’s comprehensive plan. The list of city projects was developed by selecting projects from the 2013-2018 Transportation Improvement Program (TIP) and long range transportation plans for each jurisdiction. The projects had to meet the criteria of having lane capacity expansions, new roads, or street extensions to be placed on the list. Appendix C also includes four tribal road improvement projects.

Key to project listing columns

COLUMN

DESCRIPTION

City

Name of jurisdiction

Project

The title of the project

From

The starting point of the project

To

The ending point of the project

Description

Details about the project

Appendix C

Summary of City Projects Within Snohomish County

City Projects

City

Project

From

To

Description

Arlington

WSDOT - SR 531; 43rd Ave to 67th Ave

43rd Ave NE

67th Ave NE

Preliminary planning complete, working on design pending additional funding(Widen to 5 lanes in '08 TE) (4 lanes)

Arlington

WSDOT - SR 531: 67th Ave to SR 9

67th Ave NE

SR 9

Work with WSDOT on preliminary planning activities - widen to 4 lanes, 6' sidewalk on the south and an 8' nonmotorized path on the north connecting to the Centennial Trail at the intersection of 67th and SR 531

Arlington

Smokey Point Blvd 200th St NE to SR 530 PLANNING (Widen to 3 lanes)

200th St NE

SR 530

(See attached project map) Planning and coordination with West Arlington Plan to Determine Improvements (Widen to 3 lanes)

Arlington

Smokey Point Blvd 175th Pl to 200th St NE PLANNING (Widen to 5 Lanes 175th to 188th then 3 lanes 188th to 200th)

175th Pl

200th St NE

(See attached project map) Planning and coordination with West Arlington Plan to Determine Improvements (Widen to 5 Lanes 175th to 188th then 3 lanes 188th to 200th)

Arlington

Cemetery Rd – 47th Ave to 67th Ave

47th Ave

67th Ave

Widen to 3 lanes

Arlington

Arlington Valley Road - 67th Ave NE to 204th St NE

67th Ave NE

204th St NE

New 3 lane industrial standard road connecting 67th Ave NE to 204th St NE. Low impact design

Arlington

Airport Blvd - Extend 51st Ave to 188th Street (PHASE I & II) (5lanes from South City limits to 176th where it curves NW) (3 lanes from 176th to 188th)

SR 531

188th St

(See attached project map) Seeking funding for Phase II. New Arterial extending from SR 531 North to 188th Street. (5 lanes from South City limits to 176th where it curves NW) (3 lanes from 176th to 188th)

Arlington

63rd Ave NE – SR 531 to 188th St NE

SR 531

188th St NE

Widen to 3 lanes

Arlington

59th Avenue NE – SR 531 to 195th

SR 531

195th st

Widen to 3 lanes

Arlington

59th Ave – 195th St to Cemetery Rd

195th St

Cemetery Rd

3 lane road extension (verify possibility with Airport)

Arlington

51st Avenue NE – SR 531 to 164th Street NE

SR 531

164th St NE

Widen to 3 lanes

Arlington

47th Ave NE - 188th St NE to Cemetery Rd

188th St NE

Cemetery Rd

Widen to 3 lanes

Arlington

43rd Ave – 172nd St to 162nd St

172nd St

162nd St

New 3 lane connection

Arlington

188th St NE – Smokey Point Blvd to 47th Ave

Smokey Point Blvd

47th Ave

Widen to 3 lanes

Arlington

188th St NE - 59th Ave NE to 67th Ave NE

59th Ave NE

67th Ave NE

Widen to 3 lanes

Arlington

186th St NE - SR 9 to City Limits

SR 9

City Limits

New 2 lane connection with sidewalks both sides. The total project estimate is $5M and was prepared by Snoh. County. The City's portion (SR 9 to CL) is $2M

Arlington

180th St NE – 59th Ave NE to 67th Ave NE

59th Ave NE

67th Ave NE

Widen to 3 lanes

Arlington

172nd St NE - SR 9 to 91st Ave

SR 9

91st Ave

Widen to 3 lanes

Arlington

162nd St - Smokey Point Blvd to 63rd Ave

Smokey Point Blvd

63rd Ave

3 lanes road extension (ECON DEV)

Bothell

Bothell Way (Formerly SR 527) Widening: NE 188th Street SE to 240th Street SE

NE 188th St

240th St SE

Road widening to a 5 lane configuration with intermittent median landscaping where feasible. Due

Bothell

SR 527: SR 524 to I-405 SB Lane and Intersection Improvements

SR 524

I-405

Add a third southbound lane as well as provision for nonmotorized and access management enhancement along the corridor.

Bothell

Bothell Way (Formerly SR 527) Widening: 240th Street SE to 228th Street SE

240th Street SE

228th Street SE

Widen to 5 lanes

Bothell

228th Street widening from 19th Avenue SE to 39th Avenue SE

19th Ave SE

39th Ave SE

Additional lane eastbound, lane westbound, & center turn lane on 228th Street between 19th Avenue SE and 39th Avenue SE. (Total 5 lanes)

Bothell

20th Ave SE Extension Feasibility Study (SR-524 to 214th) (2 lanes)

SR 524

214th St SE

Building a roadway with a collector designation to connect 20th Ave SE in the Canyon Park Business center north to the Maltby Road (SR 524). (2 lanes)

Bothell

35th Ave SE

240th St SE

228th St SE

Widen to 3 lanes

Edmonds

238th Street SW, SR104 - 84th Avenue W

SR 104

84th Ave W

Widen to three lanes with curb, gutter, and sidewalk (as per Pine Street Ferry Access Study)

Edmonds

228th Street SW, SR99 - 76th Avenue W

SR 99

76th Ave W

Construct connection of 228th Street SW between SR 99 and 76th Avenue W (Three lanes)

lanes with curb, gutter, and sidewalk). Install traffic signal at 228th Street SW and SR 99. Install median on SR 99 to prohibit SB LT movements at 76th Ave W.

SR 99.

Everett

US-2 Trestle widening from I-5 to SR 204

I-5

SR 204

Widen the Trestle to 3 lanes in each direction (2 GP & 1 HOV)

Everett

SR-527 widening: 112th to 132nd

112th St SE

132nd St SE

Widen to 5 lanes

Everett

SR 526/ Hardeson Road Interchange

Only for Boeing peak direction (SEE ATTACHED DRAWING) (Half Diamond) WB off-ramp to 80th St SW & EB on-ramp lanes - one from Hardeson Rd & another one from W Casino Rd

Everett

South Broadway: SR 526 to 41st Street

SR 526

41st St

Adds capacity by adding additional lanes from current 2 to a 3 lane configuration with improved LT handling at key intersections. Adds bike lanes and sidewalks for nonmotorized capacity.

Everett

SE Everett Mall Way (SR 99 to SR 526)

SR 99

SR 526

Adds Capacity by extending a NB RT pocket into a full length auxiliary lane.

Everett

Riverfront (Simpson) Site Access Improvements (Street) (2 new lanes)

(See attached project map) New access and capacity to mixed use development site. (This is the main access to the Riverfront Development site.) 2 new lanes

Everett

East Marine View Dr.: I-5 to Broadway

I-5

Broadway

Project Complete; added lane capacity, improved truck access and nonmotorized capacity. Already completed, increased from 2 lanes to: 3 lanes north of 16th and 4 lanes south of 16th

Everett

Chestnut St. /Eclipse Mill Road. Improvements (Pacific to 36th)

Pacific Ave.

36th Street

(See attached project map) Conversion of informal gravel access road to full design collector street. (2 lanes)Provides lane capacity (2 new lanes)to new development site. (This is the north end access to the Riverfront Development site.)

Everett

Broadway Corridor Improvements (SR 529 to SR 526)

SR 529

SR 526

Would add capacity by adding lanes, going from 2 to a 3 lane configuration and adding LT lanes at key intersections. Adds nonmotorized capacity by providing facilities for peds and bikes.

Everett

41st Over BNSF to Riverfront / Simpson

East of Smith Ave

Riverfront

Project Complete; Added to capacity to serve development. Added 2 new lanes

Everett

3rd Avenue SE Improvements (Street)

92nd Street SE

95th Street SE

New section of roadway in unopened R/W. Adds capacity and grid connectivity. Would add 2 new lanes and nonmotorized capacity.

Everett

112th Street SW-SE Street Improvements (I-5 to SR 527)

Interstate 5

SR 527

Project Completed this summer; added additional lanes from 4 to 5 lane configuration with additional turn capacity at SR 527

Everett

100th Street SW Street Improv. (4th Ave. W. to Airport)

Airport Road

4th Ave. W

Would add capacity by adding lanes; going to a 3 lane configuration

Increase from two to three lanes

Everett

100th Street SE Improvements (SR 527 to 7th Ave SE)

SR 527

7th Ave SE

Would add new lanes and capacity New alignment, 3 lane capacity

Everett

100th Street SE Improvements (7th Ave to Evergreen)

7th Ave SE

Evergreen Way

Would add new lanes and capacity New alignment, 3 lane capacity

Lake Stevens

20th St SE- Phase II - roadway widening, new sidewalks, improved access (Hwy 2 to 91st Ave SE)

Hwy 2

91st Ave SE

Roadway widening (4 lanes), new sidewalks, improved access.

Lynnwood

New/Expanded Road - Poplar Extension Bridge (196th St SW to AMB)

196th St SW

Alderwood Mall Blvd

New connection 5 lanes

Lynnwood

New/Expanded Road - Maple Road Extension (AMP to 32nd Ave W)

Alderwood Mall Parkway

32nd Ave W

New connection 3 lanes

Lynnwood

New/Expanded Road - 52nd Ave W (168th St SW to 176th St SW)

168th St SW

176th St SW

Add two way center turn lane

Lynnwood

New/Expanded Road - 36th Ave W (Maple Road to 164th St SW)

Maple Road

164th St SW

not much new capacity; conversion of 4 way stop at 172nd to a roundabout; extend existing five lane section currently ending just south of maple road to the north side of maple road; align maple with 189th (currently an offset “T”)

Lynnwood

New/Expanded Road - 33rd Ave W Extension (Maple Road)

Maple Road

Maple Road

New Extension 3 lanes

Lynnwood

New/Expanded Road - 33rd Ave W Extension (33rd Ave W to 184th St SW)

33rd Ave W

184th St SW

New Extension 3 lanes

Lynnwood

New/Expanded Road - 33rd Ave W Extension (184th St SW to AMP)

184th St SW

Alderwood Mall Parkway

New Extension 3 lanes

Lynnwood

New/Expanded Road - 204th St SW (68th Ave W to SR 99)

68th Ave W

SR 99

New connection 3 lanes

Lynnwood

New/Expanded Road - 200th St SW (64th Ave W to 48th Ave W)

64th Ave W

48th Ave W

Increase from 3 lanes to 5 ONLY between Scriber Lake Road & 64th ("in the SR 99 vicinity only")

Lynnwood

NB I-5 Braided Ramps

196th St SW

I-405

Lynnwood

44th Ave W - (I-5 to 194th St SW)

I-5

194th St SW

Add Lanes - Widen to 7 lanes with 8 lanes at 196th (dual NB lefts)

Lynnwood

200th St SW - (40th Ave W to 48th Ave W)

40th Ave W

48th Ave W

Add Lanes - Widen to 5 lanes

Lynnwood

196th St SW Improvements

Scriber Lk Rd

48th Ave W

Likely Beyond 20 years out according to Lynnwood Planner (Widening from 5 to 7 lanes)

Lynnwood

196th St SW Improvements

SR 99

Scriber Lk Rd

Add lanes - 5 lanes WB and EB at Scriber. 6 Lanes at WB approach at SR99. 5 lanes at EB approach at SR99.

Lynnwood

196th St SW (SR-524) - (37th Ave W to 48th Ave W)

37th Ave W

48th Ave W

Widen from 5 to 7 lanes

Lynnwood

194th St SW - (33rd Ave W to 40th Ave W)

33rd Ave W

40th Ave W

New Road - 2 Lanes

Lynnwood

176th St SW Road Diet

52nd Ave W

44th Ave W

The project will restripe 176th Street SW from four lanes to three lanes (two through lanes and one center turn lane) with bicycle lanes between 52nd Avenue W and 44th Avenue W.

Marysville

WSDOT - SR 529 EBEY SLOUGH BRIDGE REPLACEMENT - (COMPLETED) REPLACE EXISTING 2 LANE SWING SPAN BRIDGE WITH A 4-LANE FIXED-SPAN BRIDGE

(COMPLETED) REPLACE EXISTING 2 LANE SWING SPAN BRIDGE WITH A 4-LANE FIXED-SPAN BRIDGE

Marysville

SUNNYSIDE BLVD.: 47TH AVE. NE TO 52ND ST. NE - TWO GENERAL PURPOSE LANES IN EACH DIRECTION WITH A TWO-WAY LEFT TURN LANE, AND CURB, GUTTER AND SIDEWALK

47TH AVE. NE

52ND ST. NE

TWO GENERAL PURPOSE LANES IN EACH DIRECTION WITH A TWO-WAY LEFT TURN LANE, AND CURB, GUTTER AND SIDEWALK

Marysville

STATE AVENUE: 100TH ST. NE TO 116TH ST. NE - WIDEN TO 5 LANE SECTION WITH CURB, GUTTER AND SIDEWALK, AND REPLACE QUILCEDA OVERCROSSING

100TH ST. NE

116TH ST. NE

WIDEN TO 5 LANE SECTION WITH CURB, GUTTER AND SIDEWALK, AND REPLACE QUILCEDA OVERCROSSING

Marysville

STATE AVE: 116TH ST. NE to 136TH ST. NE - CONSTRUCT EASTERN 2 LANES FOR A FULL 5 LANE ROADWAY SECTION

116TH ST. NE

136TH ST. NE

CONSTRUCT EASTERN 2 LANES FOR A FULL 5 LANE ROADWAY SECTION

Marysville

SR 529 / INTERSTATE 5 INTERCHANGE EXPANSION - CONSTRUCT NEW NORTHBOUND OFFRAMP FROM I-5 TO SR 529 AND NEW SOUTHBOUND ON RAMPS FROM SR 529 TO I-5

I-5 / SR 529

SR 529-State Ave / I-5

CONSTRUCT NEW NORTHBOUND OFFRAMP FROM I-5 TO SR 529 AND NEW SOUTHBOUND ON RAMPS FROM SR 529 TO I-5

Marysville

LAKEWOOD TRIANGLE ACCESS / 156TH ST OVERCROSSING - (COMPLETED) CONSTRUCT I-5 OVERCROSSING AT 156TH ST. NE AND CONNECTING ROADWAY BETWEEN TWIN LAKES BLVD. AND STATE AVE.

(COMPLETED) CONSTRUCT 2 lane I-5 OVERCROSSING AT 156TH ST. NE AND CONNECTING ROADWAY BETWEEN TWIN LAKES BLVD. AND STATE AVE.

Marysville

Ingraham Blvd - Major Widening

74th Ave NE

81st Ave NE

Widen to 5 lane arterial including bicycle and pedestrian facilities.

Marysville

Downtown (First St) Bypass -New Roadway

State Ave/1st St

47th Ave/Sunnyside Blvd

(See attached project Map) Construct 5 lane arterial including pedestrian facilities. (State Ave/1st St to 47th Ave/Sunnyside Blvd)

Marysville

88TH STREET NE: STATE AVE. TO 67TH AVE. NE - WIDEN TO A 5 LANE ROADWAY SECTION WITH IMPROVEMENTS AT ARTERIAL INTERSECTIONS. IMPROVEMENTS BY INTERLOCAL AGREEMENT

STATE AVE

67TH AVE. NE

WIDEN TO A 5 LANE ROADWAY SECTION WITH IMPROVEMENTS AT ARTERIAL INTERSECTIONS. IMPROVEMENTS BY INTERLOCAL AGREEMENT

Marysville

67th Ave NE Connector - New Roadway

67th Ave NE/44th St NE

71st Ave NE/40th St NE

Construct 2 lane arterial including bicycle and pedestrian facilities.

Marysville

54th St NE/ 55th Pl NE - New Roadway

83rd Ave NE

Whiskey Ridge Trail (East of 80th Ave NE)

NEW Connector with bicycle and pedestrian facilities. (2 lanes)

Marysville

51ST AVENUE NE: 84TH ST. NE TO 88TH ST. NE - NEW 3 LANE MINOR ARTERAL

84TH ST. NE

88TH ST. NE

NEW 3 LANE MINOR ARTERAL

Marysville

51ST AVENUE NE: 160TH ST NE TO ARLINGTON CITY LIMITS - WIDEN EXISTING ROADWAY FROM TWO LANES TO 5 LANES WITH CURB, GUTTER, SIDEWALK, BICYCLE AND PEDESTRIAN FACILITIES

160TH ST NE

ARLINGTON CITY LIMITS

WIDEN EXISTING ROADWAY FROM TWO LANES TO 5 LANES WITH CURB, GUTTER, SIDEWALK, BICYCLE AND PEDESTRIAN FACILITIES

Marysville

51st Ave NE - Major Widening

152nd St NE

160th St NE

Widen to 5 lane arterial including bicycle and pedestrian facilities.

Marysville

43rd Ave NE - New Roadway

152nd St NE

Marysville City Limits

Construct 2 lane arterial for Smokey Point Master Plan. Specific alignments to be determined.

Marysville

40TH STREET NE: SUNNYSIDE BOULEVARD NE TO SR9 - IMPROVEMENTS CONSISTING OF ONE OR TWO GENERAL PURPOSE LANE EACH DIRECTION AND SHOULDER TO PROVIDE ARTERIAL CONNECTIVITY

SUNNYSIDE BOULEVARD NE

SR9

(NEW ROAD) IMPROVEMENTS CONSISTING OF ONE GENERAL PURPOSE LANE EACH DIRECTION AND SHOULDER TO PROVIDE ARTERIAL CONNECTIVITY

Marysville

40TH ST NE/87th AVE NE/35th ST NE: 83RD AVE NE TO SR 9 - 3 LANES FROM 71ST TO 83RD AVE.; 5 LANES FROM 83RD TO SR 9 CONNECTING TO NEW WEST LEG OF SR 92 INTERSECTION

83RD AVE NE

SR 9

3 LANES FROM 71ST TO 83RD AVE.; 5 LANES FROM 83RD TO SR 9 CONNECTING TO NEW WEST LEG OF SR 92 INTERSECTION

Marysville

27TH AVE NE EXTENSION FROM 156TH ST NE TO 166TH ST NE - CONSTRUCT A NEW ROADWAY ALIGNMENT TO CONNECT 156TH ST NE TO 166TH ST NE

156TH ST NE

166TH ST NE

CONSTRUCT A NEW 2 LANE ROADWAY ALIGNMENT TO CONNECT 156TH ST NE TO 166TH ST NE

Marysville

172nd St NE (SR 531) - Major Widening

27th Ave NE

11th Ave NE

Widen to 4 lane arterial including bicycle and pedestrian facilities.

Marysville

160th St NE - New Roadway

Smokey Point Blvd

59th Ave NE

Construct 2 lane arterial for Smokey Point Master Plan. Specific alignments to be determined.

Marysville

156th/152nd St NE - New Roadway

Smokey Point Blvd

51st St NE

Construct 4 lane arterial including bicycle and pedestrian facilities.

Marysville

156TH STREET NE: STATE AVENUE TO 51ST AVE. VIC. - WIDEN TO 5 LANES CURB, GUTTER, AND SIDEWALK

STATE AVENUE

51ST AVE. VIC.

WIDEN TO 3 LANES CURB, GUTTER, AND SIDEWALK

Marysville

156th St NE Interchange @ I-5

CONVERT THE 156TH ST NE OVERCROSSING INTO A FULL SINGLE POINT PE 750 UNFUNDED PE 750 UNFUNDED ALL 40,000 UNFUNDED

URBAN INTERCHANGE WITH INTERSTATE 5

Marysville

152ND STREET NE: STATE AVE. TO 43RD VIC. - WIDEN FROM 2 TO 3 LANES

STATE AVE.

43RD VIC.

WIDEN FROM 2 TO 3 LANES

Marysville

152nd St NE - Major Widening

51st Ave NE

67th Ave NE

Widen to 4 lane arterial including bicycle and pedestrian facilities.

Marysville

152nd Connector - New Roadway

152nd St NE

156th St NE

Construct 3 lane arterial for Smokey Point Master Plan. (See attached project map) Specific alignments to be determined.

Marysville

*152ND STREET NE: 43rd AVE. VIC. TO 67TH AVE. NE - WIDEN TO A 3 LANE ROADWAY SECTION WITH IMPROVEMENTS PE 1,000 UNFUNDED ALL 10,000 UNFUNDED AT ARTERIAL INTERSECTIONS

43rd AVE. VIC

67TH AVE. NE

WIDEN TO A 3 LANE ROADWAY SECTION WITH IMPROVEMENTS PE 1,000 UNFUNDED ALL 10,000 UNFUNDED AT ARTERIAL INTERSECTIONS

Mill Creek

East Gateway Spine Road - Construction (Diagonal SE to NW cut in the NE most corner of city)

Seattle Hill Rd between 136th & 135th

Intersection of 39th Ave SE & 132nd Ave SE

Construction of public infrastructure and central spine road in East Gateway Urban Village Area. Project elements could consist of a roadway with two 14-foot lanes, on-street parking, sidewalk,utilities, and could also include regional drainage

Monroe

Woods Creek Rd – Phase 2

Oak St

City Limit

Widen road to 3-lane section with bike lanes, curb, gutter, and sidewalk.

Monroe

Tjerne Pl - Chain Lake to Woods Creek - New Road (2 lanes)

Chain Lake Rd

Woods Creek Rd

New Roadway (2 lanes)

Monroe

Oak Street Widening

Woods Creek Rd

Old Owen Rd

Continuation of Tjerne Pl to Old Owen Rd. (2 lanes)

Monroe

E/W Connector - South of US 2 (154th (From 179th to intersection of Hill Street & Kelsey)) (2 lanes)

179th Street

Hill Street

New Roadway (2 lanes)

Monroe

Chain Lake Rd – Phase 2

North Kelsey St

Brown Rd

Widen road to 5-lane section with bike lanes, curb, gutter, and sidewalk.

Mountlake Terrace

Gateway Connector / Blvd- Construct new road from Gateway Bridge to 236th Street SW - Gateway Bridge to 236th St SW) (2 lanes)

Gateway Bridge

236th St SW

(See attached project map) Construct new road from Gateway Bridge to 236th St SW (2 lanes)

Mukilteo

Harbour Reach Drive Extension - Extend Harbour Reach Drive from Harbour Point Boulevard to the Old South Road and extend the old South Road to Beverly Park Road. Install sidewalks/walkways, street lighting, and storm drainage. (Harbour Point Boulevard t

Harbour Pt Blvd

Beverly Park Rd

Extend Harbour Reach Dr from Harbour Pointe Blvd to the old South Rd and extend the old South Rd to Beverly Park Rd. (2 lanes) Install sidewalks/walkways, street lighting and storm drainage.

Shoreline

Aurora Corridor Improvement Project – N 192nd Street to N 205th Street

192nd

205th

Add Business Access and Transit (BAT) lanes on both sides of street (2 BAT lanes), curbs, gutters, landscaping/street furnishings, sidewalks onboth sides.

Snohomish

Bickford Avenue / US 2 Interchange - Intersection realignment and Roadway Construction improvements

Intersection

US 2

Intersection realignment and Roadway Construction improvements (Crossover Onramp)

Snohomish

20th Street Extension - New alignment, Right of Way, and Roadway extension improvements - (Bickford to Lake Ave)

Bickford Ave

Lake Avenue

New alignment (2 lanes), Right of Way, and Roadway extension improvements

Stanwood

74th Ave NW Construction - Construct new 74th Ave NW with curb, gutter, utilities, and sidewalks on both sides - (267th St NW South to Pioneer Hwy)

267th St NW

Pioneer Hwy

Construct new (2 LANE) 74th Ave NW with curb, gutter, utilities, and sidewalks on both sides

Stanwood

68th Avenue extension and improvements.

280th St NW

Woodland Rd

68th Avenue extension and improvements. (2 lanes)

Tulalip

88th St NE

I-5

19th Ave NE

Extend 88th street NE with a new six lane roadway to intersect with 19th Ave NE.

Tulalip

27th Avenue - Marine Dr to 88th St - Capacity/Safety, Widen roadway to 3 or 5-lane section – ped/bike/transit improvements

Marine Dr

88th St

Capacity/Safety, Widen roadway to 5-lane section – ped/bike/transit improvements

Tulalip

27th Avenue – 88th St to 116th St - Capacity/Safety, Widen roadway to 3 or 5-lane section – ped/bike/transit improvements

88th St

116th St

Capacity/Safety, Widen roadway to 3 lane section – ped/bike/transit improvements

Tulalip

19th Avenue NE - Capacity, Widen to 3-lane and extend to new east-west roadway

Marine Dr NE

116th St NE

Capacity, Widen to 3-lane and extend to new east-west roadway

roadway

Woodinville

Woodinville-Snohomish Widening - Widen the road to a 5-lane section with curb, gutter, sidewalk, bike lanes, illumination and new traffic signals - (140th Ave NE to North City Limits)

140th Ave NE

North City Limits

Widen the road to a 5-lane section with curb, gutter, sidewalk, bike lanes, illumination and new traffic signals